More

    WR achieves another milestone during lockdown

    Must Read

    Opposition from BJP supporters of Ward 18 in Vadodara over inclusion of Congress councillor into the party

    Party president assure them of not any such entry into the party BJP leaders...

    Vadodara police organise rally to spread awareness about She team

    Vadodara police on Saturday conducted a rally in the city area to spread awareness about the newly...

    2.58 lakhs Mediclaim scam of producing false bills for knee surgery unearthed in Vadodara

    Detention of doctor, laboratory employee and husband of mediclaim holder The insurance company had...

    Complete the raft foundation work on the West side of Delisle ROB at Lower Parel

    In yet another major accomplishment, Western Rly has added a milestone to its kitty by completing the Raft foundation works on the west side of Delisle Road Over Bridge at Lower Parel station. They complete the work inspite of the lockdown restrictions and the heavy rains being a spoiler for the past few days.
         
    According to a press release issued by WR CPRO Sumit Thakur, the dismantling work of the spans over railway tracks on the Railway portion was taken up  by W. Rly and was completed in February 2019, in a record time frame of five months period. The work of dismantling of abutments was completed in the month of June, same year after the removal of encroachments by MCGM.

    Western Railway awarded the contract for rebuilding the Railway portion of ROB at a cost of Rs. 87 Cr. and the physical work of laying foundations for Railway span was taken up after the monsoons, in November 2019. The foundation work on east side was completed in May 2020, amidst the nationwide lockdown due to the Corona pandemic. Considering the priority and importance of the work, all efforts were made by Western Rly to continue the execution of this work, despite Covid and the monsoons.

    In continuation of this effort, a major milestone was achieved on 19th July, 2020, whereby, the Raft foundation work on the west side was completed, even though the work had been affected due to heavy rains in the past few days. A total of 625 cum of concreting was done in 14 hrs by a team of 93 engineers, supervisors & labourers and 92 MT of stainless-steel r/f was used in this foundation. It is worth mentioning that the concreting of this Foundation was a critical activity to adhere to the timeline fixed for completion of this ROB.

    Further, the work of Railway portion of ROB is targeted to be completed in the next 10 months excluding monsoon i.e. by March 2021. The Girder fabrication for the ROB is being done at RDSO approved workshop at Kota and around 1800MT (Out of total 2500 MT) structural steel of E450 Grade have already been received in workshop at Kota.

    Thakur stated that with regards to the work pertaining to the dismantling and re-building of approaches to be undertaken by MCGM, it was informed that MCGM has awarded tender on 27th January, 2020 for this work, keeping the completion period of eighteen months (18 months) excluding monsoon.

    There are total 3 approaches, two on West where work of dismantling and rebuilding can be fully executed by MCGM and the approach on East is planned to be used for assembly and launching of steel girders assemblies as weight of each girders assembly will be 1200 MT (88m x 16m x 12m) which cannot be lifted and launched with cranes and need to be pushed from East approach of ROB. This East approach will be made available to MCGM, only after launching of girders by Railway and till that time MCGM can complete dismantling and rebuilding of two approaches of West side.  As of now, dismantling work of West side approaches have been completed by MCGM.
         
    It’s worth mentioning that the Delisle Road Over Bridge at Lower Parel which is owned by the MCGM and crosses over the railway tracks, was found to be unsafe following a safety Audit conducted in July 2018. Hence, the Delisle ROB was closed for public use, both for vehicular traffic & pedestrians with effect from 24th July, 2018, for undertaking repairs to the bridge on priority basis. It was decided that the work of dismantling and rebuilding of Railway portion of this ROB will be done by Railway and the work of approaches dismantling and rebuilding will be executed by MCGM.

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here

    This site uses Akismet to reduce spam. Learn how your comment data is processed.

    Latest News

    Old Rs 100 notes to be withdrawn from circulation by RBI in March 2021

    The Reserve Bank of India (RBI) is planning to withdraw the old series of currency notes including...

    Vadodara police organise rally to spread awareness about She team

    Vadodara police on Saturday conducted a rally in the city area to spread awareness about the newly formed She Team. The special...

    2.58 lakhs Mediclaim scam of producing false bills for knee surgery unearthed in Vadodara

    Detention of doctor, laboratory employee and husband of mediclaim holder The insurance company had lodged a complaint at the...

    Old Rs 100 notes to be withdrawn from circulation by RBI in March 2021

    The Reserve Bank of India (RBI) is planning to withdraw the old series of currency notes including Rs 100, Rs 10, and...

    19 years old Srishti Goswami set to become CM for 1 day of this State

    Haridwar-based teenager Shristi Goswami will take charge as Uttarakhand Chief Minister for one day on January 24 on the occasion of National...

    More Articles Like This

    - Advertisement -